CERC Grants JSW Renew 30-Day Extension for Wind Turbine Commissioning After Equipment Failure
The project developer had approached the Commission after being unable to complete commissioning activities for the remaining 10 WTGs due to a failure.
Read the full articleYou might also wanna read

How CERC Plans to Revive 16 GW of Stalled Renewable Energy Projects
In a significant move aimed at easing India's growing transmission bottleneck, the Central Electricity Regulatory Commission ( CERC ) has un

CERC Order Offers Clarity On Sale of Infirm Power In Delayed Hybrid Projects
The Central Electricity Regulatory Commission (CERC) has allowed TP Saurya Ltd. to continue selling infirm power generated from the 100 MW s
JSW Energy secures 200 MW/400 MWh BESS order from Bondada Renewable Energy
JSW Energy Ltd has secured an order worth INR 443.74 crore from Bondada Renewable Energy to supply 200 MW/400 MWh of battery energy storage

ReNew, Mitsui's 320 MW RTC Hybrid Project Secures US$730 Million Refinancing
ReNew and Mitsui's 320 MW round-the-clock (RTC) hybrid renewable energy project in India has secured refinancing through a US$730 million gr

JSW Energy Subsidiary Wins INR 444 Crore BESS Order from Bondada Renewable Energy
JSW Energy has announced that its step-down subsidiary, JSW Energy PSP Eleven (JEPEL), has secured an order worth ₹443.74 crore from Bondada

CERC Directs CTUIL to Restore Connectivity for Pace Digitek's 100 MW Solar-BESS Project
The Central Electricity Regulatory Commission (CERC) has condoned a two-day delay by Pace Digitek Limited in submitting Connectivity Bank Gu

Comments
Sign in to join the conversation.
No comments yet. Be the first.